Construction Defect Remediation Project
Cedar Park Condominiums
Redmond, WA $2 Million
Location
Redmond, WA
Project Value
$2 Million
Type
Construction Defect Remediation Project
Project Scope
Repairs to the decks and buildings.
Challenges
The amount of settlement received to repair the construction defects was not adequate. The project required extensive value engineering to complete necessary repairs within a realistic construction budget.
Results
Although the project took longer than expected, all work was completed within the original set construction budget without the need to supplement through special assessment.